Question: 1 / 90

What role do lower-level components of WBS play in bottom-up estimation?

They serve as a safety net for higher-level projects

They are used to inform high-level risk assessments

They provide specific inputs for cost and duration estimates

Lower-level components of the Work Breakdown Structure (WBS) play a crucial role in providing specific inputs for cost and duration estimates. By breaking down a project into smaller, more manageable tasks, these components allow project managers to create a detailed understanding of the resources required and the time necessary to complete each specific activity. This granularity enhances the accuracy of estimates since it is easier to assess the cost and effort involved in smaller tasks.

When employing bottom-up estimation, project teams gather detailed information regarding each component, which includes labor costs, materials, and potential risks associated with each task. This method ensures that estimates are grounded in reality based on the actual work that needs to be performed, leading to a more reliable overall project estimate. Moreover, by focusing on the specifics of each lower-level component, uncertainties can be minimized, and potential issues can be identified early in the planning process.

In contrast, other roles of WBS components, such as serving as a safety net for higher-level projects or informing high-level risk assessments, may not utilize the same level of detail necessary for accurate estimation. Additionally, disregarding lower-level components in favor of expert opinions can lead to estimates that overlook critical activities or resources, resulting in budget overruns or schedule delays. Thus, the

They are often disregarded in favor of expert opinions